Robbins TBM Sets New Record
The Robbins TBM reached high rates of 870 m (2,855 ft) per month and 58 m (188 ft) per day, setting a record for TBM tunneling in India, for a water tunnel in Mumbai.

On January 21, 2014, a Robbins Main Beam TBM completed one of the longest and deepest water supply tunnels in Asia, the Mumbai Water Tunnel. The 6.25 m (20.5 ft) diameter machine displayed excellent performance throughout the 8.3 km (5.2 mi) bore, and achieved impressive advance rates along the way.

Joint venture contractor Unity-IVRCL (UIJV) was pleased with the hard rock machine and the continuous support provided by Robbins during the project.?The Robbins TBM was good with hard rock, and we reached high rates of 870 m (2,855 ft) per month and 58 m (188 ft) per day, both records for TBM tunneling in India. We were able to achieve this due to the good performance of the machine and a conveyor system for muck haulage in place of conventional methods, said Pravin Titare, General Manager, Unity Infraprojects.

Robbins provided both the TBM and conveyor system for the project, as well as field service personnel to monitor the equipment and assist with daily upkeep and inspection.?The Robbins crew helped us commission and start boring on schedule, and the Robbins TBM operators did a great and skillful job maintaining tunnel alignment. Because of this, UIJV received a good report from our client Municipal Corporation of Greater Mumbai (MCGM),? said Titare.

Although the machine was ultimately a success, it did experience its fair share of challenges during the 21-month bore. Difficult ground, including basalt rock, fractured ground, and water inflows, was encountered throughout the tunnel.?The geology was particularly bad at times. Our team took all precautionary measures and advanced slowly. We maintained good ventilation throughout execution and used a good dewatering system,? said Bipin Arey, General Manager, IVRCL.

Ground support also played a critical role, said Titare,?The TBM was very safe in the adverse geological conditions. The rock support system and ring beam erector were helpful to reduce downtime and allowed us more production time.? Challenging ground conditions, combined with the sheer depth of the 109 m (357 ft) tunnel, made the machine?s excellent advance rates especially notable.

Now completed, the water transfer tunnel will provide Mumbai?s approximately 20.5 million residents with a consistent flow of clean drinking water, even during the seasonal monsoons that formerly contaminated the city?s water resources.

Robbins provided both the TBM and conveyor system for the project, as well as field service personnel to monitor the equipment and assist with daily upkeep and inspection.