AERB Approves First Approach to Criticality for RAPP-8

The Atomic Energy Regulatory Board (AERB), India’s nuclear safety regulator, has approved the First Approach to Criticality (FAC) for Rajasthan Atomic Power Project Unit-8 (RAPP-8), marking a key regulatory milestone for the project. The approval was reported on 20 November 2026 and permits the unit to move towards the next stage of commissioning.

RAPP-8 is located at the Rawatbhata Nuclear Power Plant in Rajasthan’s Chittorgarh district. It is the fourth unit in India’s indigenously designed and developed 700 MW pressurised heavy water reactor (PHWR) series, placing the project within the country’s programme to build domestically developed nuclear generation capacity. The reactor technology is based on the pressurised heavy water design used for India’s nuclear power expansion.

The regulatory review covered the reactor’s design and construction, commissioning test results and preparedness for operations. It involved detailed assessments by AERB and its safety review committees, inspections carried out under the regulatory process, and deliberations by the AERB Board before approval was granted.

The FAC clearance allows the project to proceed towards subsequent commissioning activities. These activities will take the unit through the remaining steps required before it can begin commercial electricity generation, subject to the applicable regulatory requirements and further approvals.

The approval indicates that the unit has completed the safety reviews required for this specific commissioning stage. It does not itself represent the start of commercial operations, but establishes the regulatory basis for moving RAPP-8 closer to that stage. Further commissioning work will continue under AERB oversight at the Rawatbhata site.