Chennai-Bengaluru Highway Expansion Delayed Until August 2027
The six-laning of the 34.5-km Sriperumbudur-Karaipettai section of the Chennai-Bengaluru highway remains incomplete eight years after work began, causing severe hardship for commuters. The National Highways Authority of India (NHAI) has missed several deadlines and has completed only eight of the 17 planned flyovers, bridges and vehicular underpasses. The agency has set August 2027 as the revised completion deadline.
The existing 15 m carriageway narrows to 7.5 m over nearly 3.5 km, where traffic is diverted to service lanes to enable construction of underpasses at Mambakkam and near SIPCOT in Sriperumbudur. Vehicles take between 60 and 90 minutes to cover the 10 km stretch between Sriperumbudur and Sunguvarchathiram, with conditions worsening during weekends and festival periods.
During the recent Deepavali period, queues extended up to 9 km between Sunguvarchathiram and Sriperumbudur from November 5 to 10. Commuters reported that congestion persisted throughout the day despite the highway being tolled, while diversions and damaged surfaces in Sriperumbudur affected traffic movement and increased dust for bus passengers and two-wheeler riders.
NHAI officials from the Kancheepuram project unit said underpasses and flyovers at Sunguvarchathiram East and West, Santhavellore, Senthamangalam, Rajakulam, Vedal, Anna Cancer Institute and Ponnerikarai junctions had been completed and opened to traffic. Pending work at SIPCOT, Mambakkam, Enathur, Meenakshi Medical College junction, Beemanthangal and other locations is at various stages, with limited road closures permitted by the police affecting construction progress.
Officials said minor soil procurement issues had affected the project and retaining walls had been built at two locations. Of the 34.5 km covered by the pending works, 23.3 km had been completed and the remaining 11.22 km is scheduled for completion by August 2027. The wider six-laning project covering 70 km between Sriperumbudur and Walajahpet began towards the end of 2018 at a cost of Rs. 11.88 bn.