Implementation of PRL at KAPP-3
The seventh ring of Kakrapar Atomic Power Project-3 (KAPP) was successfully installed and is among the largest (dimensionally) engineered structures to have been lifted and placed in such a manner in India.

The 700 MWe Indian pressurised heavy-water reactors (PHWRs) that are being constructed at the Kakrapar Atomic Power Project (KAPP) 3 and 4, and RAPP 7 and 8 have a number of firsts design features towards enhancement of safety. The steel liner on inner containment (IC) wall of about 50 m dia encasing reactor building is being one of them. The liner of 6 mm thick is provided for better leak tightness. The IC wall is 48 m height from the raft level to the ring beam bottom level.

The steel liner erection scheme initially used 16 liner panels of 10 m (circular length) x 5 m (height) and weighing 5.5 tonne each. These panels consist of liner plate, backing trusses and stiffeners (vertical and circumferential). Each such panel is fabricated at fabrication yard and erected by tower crane in position at the inner periphery of the IC structure one by one. After keeping all the panels and adjusting their positions, fit up, tack welding and final welding is done. This process of aligning and welding of adjacent panels becomes more and more difficult at higher elevations.

Based upon the availability of high capacity crawler crane (LR11350) and international experience in modularisation of containment liner, the feasibility of construction by preformed ring liner (PRL) was pursued, ie, assembling 16 IC liner panels at ground and erecting the same as a ring.

These studies also established that significant savings in steel could be affected by elimination of backing trusses required for the individual panels.

The advantages of adopting this new technique are:
  • Majority of fabrication can be done at ground, resulting in better conditions in terms of achieving quality welding with higher safety.
  • Better constructibility with decreased congestion of the IC wall due to the absence of trusses.
  • Parallelisation in construction work can be realised leading to substantial construction time minimisation.
  • The PRL concept was implemented from seventh lift of IC wall of unit-3. These panels are fabricated in the yard and assembled at ground level in assembly area, which is near to the reactor building-3. For lifting of the whole assembly (i.e. PRL), spider was fabricated and load tested in advance.
  • The seventh ring of KAPP-3 was successfully installed for the first time on 31 December 2013, and would count as the largest (dimensionally) engineered structures to have been lifted and placed in such a manner in India. This effort epitomises the team work and spirit of the Indian nuclear industry.

    Salient Features
  • PRL is of 50 m in diameter with a height of 5 m and weighing around 80 mt.
  • Spider (strong back) which is used for lifting the PRL is load tested up to 140 mt.
  • Evener beam, which was used as intermediate structural member between spider and crane, is weighing 9 mt.
  • Total assembly has been lifted by Liebherr crane (LR 11350) of NPCIL.
  • Total weight handled by the crane: During PRL erection: 172 mt