Indiabulls using Potain solution
The sales and engineering team from Manitowoc worked closely with the design and planning team at Indiabulls to come up with a perfect solution. The Manitowoc team proposed eight 10T capacity MC 205 cranes to build the three high-rise towers. As required, all of the cranes would be mounted on 1.6 m mast sections and, because of space limitations, Manitowoc proposed shorter jibs of 25 m. The team also designed a coordinated climbing plan for the course of construction, synchronising it with the placing of formwork and the completion of the building cores.