KSERC Allows Renewable Grid Connectivity Above 14.4 MW in Kerala
The Kerala State Electricity Regulatory Commission (KSERC) has ruled that distribution capacity limits prescribed for electricity consumers cannot be used to restrict grid connectivity for renewable energy projects at the 33 kV level. In an order dated November 18, the Commission said projects may receive connectivity above 14.4 MW if the proposed connection is technically feasible and meets applicable grid safety and reliability requirements.
The decision followed a petition filed by INKEL, INKEL Renewable Energy and INKEL Green Energy against the Kerala State Electricity Board (KSEB) over connectivity for renewable projects in Palakkad and Malappuram. INKEL had challenged KSEB’s restriction limiting 33 kV connectivity to 14.4 MW or 14.4 MVA.
KSEB had calculated the limit by applying a 20 per cent allowance under the Kerala Electricity Supply Code, 2014, to the prescribed 12,000 kVA consumer limit for 33 kV supply. KSERC clarified that connected load and contract demand provisions apply to electricity consumers and do not govern electricity injection from generating stations. It said higher connectivity can be granted on the basis of load flow and system studies conducted under Central Electricity Authority (CEA) standards and applicable connectivity regulations.
For INKEL’s group captive solar project at Panakkad in Malappuram, KSERC found that connectivity for 16.4 MW AC was technically feasible. The project capacity had been revised to 20.5 MWp DC, including a battery energy storage system. Because of procurement delays involving indoor 33 kV switchgear panels and a central government exemption on solar cell rules valid until December 31, 2026, KSEB was directed to provide connectivity for the commissioned capacity through a temporary arrangement at the existing 33 kV INKEL substation.
The temporary arrangement remains subject to safety requirements and electrical inspectorate approvals. KSEB was also directed to expedite the 33 kV INKEL–Othukkungal transmission line. For a proposed 36 MW solar-wind hybrid project at Vadakarapathy, INKEL has declared a maximum export limit of 25 MW but had not filed a formal connectivity application. KSERC directed the company to submit the application within 30 days, after which KSEB must complete load flow studies within 30 days of receiving complete documentation. The Commission also noted a pending power purchase agreement for a 14 MW wind component and the delayed handover of 1.5 acres for a proposed substation.