Potain tower cranes assisting on Riyadh Metro project
The first batch of tower cranes was delivered in November 2015 and the remainder was delivered at the start of 2016. The MCT 205s are currently working 20 hours a day on a two-shift basis and are working at a height of 44.4 m. All 28 cranes are expected to remain on the jobsite for the next 18 months. As part of the rental contracts, NFT is supporting the operations and maintenance of the cranes. The project is expected to be complete by 2018.