Divisional Commissioner Reviews Jammu Ring Road Works
Divisional Commissioner Jammu Vikas Kundal inspected ongoing works under the Jammu Ring Road Project on Nov 7, 2026, to assess progress on tunnels and other infrastructure components. The inspection focused on construction activity and the factors affecting implementation at project sites.
The commissioner was accompanied by Deputy Commissioner Jammu Minga Sherpa, National Highways Authority of India (NHAI) Project Director Rajiv Kumar, members of the NHAI team, the Additional Central Revenue officer for Jammu and other officials. Their presence enabled a joint review of the work being carried out by the agencies involved in the project.
During the visit, Kundal inspected Tunnel 1 and Tunnel 2, which connect Kheri with Jagti. He sought on-site feedback on the pace of construction, execution-related difficulties and other issues that were affecting the smooth progress of the works. The review covered the immediate conditions at the tunnel sites and the need for continued coordination during construction.
Rajiv Kumar briefed the commissioner on the difficulties encountered during construction of Tunnel 1. Loose soil conditions were identified as a particular challenge and were affecting the pace of work at the site. The issue formed part of the review of measures required to maintain progress across the tunnel component and other ongoing sections of the project.
Kundal instructed the NHAI project director and the executing agencies to accelerate construction across all ongoing components and maintain close coordination for timely completion. He also called for site-specific challenges to be addressed through appropriate measures, along with regular monitoring of work.
Later, the commissioner inspected Balicharan Road towards Satwari. He reviewed the condition of the road and related infrastructure aspects as part of the wider assessment of works and associated facilities in the area.