Achieving Substantial Savings in Project Costs
While planning a new manufacturing plant, substantial costs can be saved by involving ElectroMech at the plant design stage. Thermax Babcock & Wilcox experienced this at their new plant near Pune. A case study:
Thermax, headquartered in Pune, is a renowned engineering solutions provider for the energy and environment sector. The Thermax factory in Chinchwad, Pune, has several cranes from ElectroMech which are used for various applications such as loading, unloading, handling, and assembly work. ElectroMech has also been providing crane solutions to all of Thermax?s factories as well as for many of their projects.

The company has a joint venture with Babcock & Wilcox (USA), a global leader in the power generation industry, to manufacture supercritical boilers for the power sector. When the company planned to expand their operations and decided to commission a new plant near Pune, requirement for several cranes was also envisaged. This plant, spread over 4,00,000 sq m of land at Shirwal near Pune, is now operational. The manufacturing facilities are split into 3 units; a 25,000 sq m Section shop, a 16,000 sq m Panel shop and a 18,000 sq m Header shop. Satisfied with their past experience with ElectroMech, the TBW Project Engineering team approached ElectroMech at the planning and designing stage of this new plant to help craft the perfect material handling solution.

The handling challenges at TBW

While designing and constructing a new factory, consideration of overhead cranes in the plant is crucial for determining the overall specifications of the building. This is because overhead cranes run on gantry girders that are supported by the building structure. In addition to the building structure and roof itself, the entire load of the crane as well as the job being handled is borne by the factory columns. Involving ElectroMech at the factory planning stage is always beneficial since it can optimise the crane design to suit the exact requirement and plant layout. The structural engineer can then optimise the factory building based on the wheel loads and crane dimensions provided by ElectroMech.

Keeping this aspect in mind, Thermax Babcock & Wilcox (TBW) involved ElectroMech right from the conceptualisation and planning stage of the project. The company was expected to understand the process flow and recommend a suitable system for handling at each workstation as well as integrate all the material handling in the plant. Besides, TBW was also obviously expecting a technically proven material handling system that matched their applications and is cost-efficient.

Solutions from ElectroMech
The ElectroMech team worked closely with the TBW project team to understand the proposed plant layout, expected material flow, planned production volume and thoroughly evaluated handling requirements existing at each of the workstations. Through this rigorous study, several options were developed which were shared with TBW and the factory architects. Each one was evaluated for its competence to match the handling requirement, maximise production efficiency and at the same time optimise investment in cranes as well as the factory structure. Finally, an optimum solution was decided which comprised 45 cranes of different types. ElectroMech, by following a consultative approach, designed a solution that was economical, had advanced features and matched the application requirements perfectly. These cranes with capacities ranging from 10MT to 50MT integrate the entire handling operations on three shop-floors and also cover handling right from raw material storage to the final despatch area, including several fabrication and assembly stations.

Saving on project costs
An apt example of the benefit of involving ElectroMech during the planning stage can be seen in the plant?s Section shop. The highest capacity crane is 50MT, which would logically require the entire factory building to be designed for the loads exerted by this crane. However, during detailed analysis of the client?s workflow, it was apparent that the 50MT job would never traverse the entire length of the shop-floor. This allowed the structure to be optimised, so that only the necessary portion had to be built to take the load from the 50MT crane. Safety limit switches ensure that the 50MT crane does not travel with its full load to other parts of the shop. This solution gave TBW substantial saving in their structural cost for this shop. Being involved in the design stage also allowed ElectroMech to provide inputs on the workflow, so as to optimise the choice of cranes to keep costs low while achieving maximum resource utilisation.

Reduced maintenance & power consumption
For the outdoor duty gantry cranes, TBW opted for a power supply system that was more reliable and had zero maintenance compared to what was used traditionally. Typically, for a gantry crane, one uses cable reeling drums. The cable reeling drum mechanism itself can prove to be problematic in some cases as it increases maintenance. ElectroMech was able to factor in, at the time of construction itself, a way to use regular shrouded bus bars for supplying power to the outdoor gantry cranes. By this, the company has eliminated a lot of hassles which might have arisen in the future had it resorted to the cable reeling drum concept. This approach has also led to further reductions in the project cost.

Energy consumption is also reduced, as the cranes have efficient motors which ensured optimum energy utilisation. If one were to combine the total power consumption of all the cranes used throughout the TBW factory, it would be observed that there is an energy reduction of at least 15 to 20 per cent over conventional cranes.

Faster handling, Higher profits, Higher safety
ElectroMech has also supplied TBW with unique solutions like wall travelling cranes. On a shop-floor, with respect to the principles of Lean Manufacturing, waiting time is one of the prime sources of waste. Wall travelling cranes allow workers to service workstations individually without using cranes on the top. Waiting time for the crane is thus eliminated and productivity of the individual workstation is enhanced.

This is a much better solution than a semi-gantry crane, in which one end carriage runs on the gantry girder, while on the other side a leg runs on the floor. Having an end carriage running on the factory floor creates a safety hazard due to the possibilities of collisions with men, machines and material. Rail tracks or supports would also be needed on the ground, increasing the civil cost. Wall travelling cranes have no legs and travel in the air independently on their own supporting structure integrated with the factory building, thus enabling efficient and safe layout of the workstation. Integrating the wall travelling cranes into the layout was not only a value addition to the project, but also saved the client substantial process time due to higher crane availability.

Customer satisfaction
Though material handling forms a critical part of any workshop, Lean Manufacturing philosophy dictates its reduction. By taking cognisance of what needs to be done on a shop-floor, arranging processes accordingly and by optimising speeds and geometries of cranes, material handling time can be drastically reduced. This needs to be planned in the early stages of the project to derive maximum advantage. The TBW management was extremely happy with their selection of ElectroMech as a solutions partner and for involving it right from the beginning. They could successfully achieve all their objectives and build a manufacturing facility which adheres to the Lean Manufacturing principles.

How TBW benefited from ElectroMech solution

  • Initial study helped in optimising crane designs which saved on capital cost
  • Energy efficient cranes to save on running cost by almost 20%
  • Well engineered cranes ensure high level of safety
  • Smooth material flow through complete integration of handling in the entire plant

Challenges Solution
Optimise on building structure by
designing the most efficient
material handling systems
45 cranes which integrate handling right
from raw material storage
yard to despatchbay
Ensure optimum utilisation of each
crane to restrict the number of cranes required
Zone protection systems were
introduced to help save on the
structural cost and enhance safety
Ensure integration of handling
in the entire plant
Wall travelling cranes at critical
workstations to avoid waiting for crane
availability
Waiting time for the availability of
the crane at every workstation
should be zero or minimum
Use of inverter drives to reduce
power consumption
Rugged yet elegant looking cranes
to suit the overall aesthetics of the plant
Optimised crane designs to
reduce weight and power consumption