Construction projects designed to be completed in an extremely short time are demanding
in many respects. They require precise planning, a high degree of process reliability and
reliable machinery. Of course, they also demand experience and competence from users
and experts. All these parameters were important for rehabilitating a 3.6 km section of the
A3 motorway near Duisburg, too. As this busy commuter route carries some 120,000
vehicles on weekdays, the responsible highways authority, Straßen.NRW, decided to
carry out the rehabilitation project by closing the road completely.
The work started with a full road closure in both directions. After that, the right-hand
carriageway, which is made of concrete and did not require rehabilitation, was separated
from the adjacent asphalt lane using a side milling wheel. Four Wirtgen cold milling
machines of the W 210i, W 220i and W 250i types started removing the surface and
binder courses which required rehabilitation. A total of 20 hr was scheduled for this part
of the work, and asphalt paving started before milling work was even complete. Paving
had to be complete to allow enough time for follow-up tasks such as the application of
road markings. The route was set to be opened to traffic to enable commuter traffic in this
densely populated area to start the week normally.
Six Vögele pavers in service
A window of just 27 hr was available to pave an area of 60,000 sq m. The team from
contractors met this challenge with a total of six Vögele pavers. Two SUPER 2100-3i
machines first paved the binder course. One of the two Highway Class pavers worked in
one direction of travel, whilst the other paver simultaneously started at the other end of
the job site, working in the opposite direction. The surface course consisting of low-noise
stone mastic asphalt (LOA) was then paved by two SUPER 1800-3i SprayJet machines
using the ‘hot to hot’ method.
Three mixing plants were commissioned with production of the asphalt to guarantee
material supply on this very tight schedule, with a further plant in reserve in case it was
needed. As many as 130 trucks made 500 trips to transport the hot asphalt to the job site
between the junctions at Duisburg-Kaiserberg and Breitscheid. In all, 16,000 tonne
asphalt (12,000 tonne for the binder course and 4,000 tonne for the surface course) had to
be produced, transported and paved.
Ensuring continuous supply of mix
Two Vögele PowerFeeders of the MT 3000-2i Offset type accepted the mix from the
trucks to guarantee a continuous supply to the pavers. Use of two feeders was essential on
this time-critical project: as the material feeder operators were coordinating unloading,
this allowed the paver operators to give their full attention to the paving process. Given a
whole 500 truckloads in a few hours and the high pave speeds, this was essential.
Emulsion spraying and asphalt paving in one operation
The Vögele SUPER 1800-3i SprayJet spray pavers also ensured an efficient process: they
sprayed on the bitumen emulsion and paved the asphalt surface course in just one
operation. In addition to saving time, paving the A3 with Vögele SprayJet technology had
other benefits: as the freshly-applied film of emulsion was paved over immediately
following application, construction vehicles were unable to drive over the binder film and
damage it. This improves interlocking and thus also the service life of the road.
Ready for traffic
The smooth interaction of the team and the machine technology from Wirtgen and
Vögele meant that finally, everything was ready: the A3 motorway was reopened to
traffic. All those involved were hugely relieved to have managed the tight schedule.
“That was an incredible performance by the whole team. Everyone supported everyone
else,” said
Construction Manager Niklas Lehmann, after the project was complete.